The key points
- The duty is in section 11(1) of the RERA Act: four items kept up to date each quarter on the project's web page.
- The promoter files it on the state Authority's portal, using the login issued at registration.
- Deadlines, formats and penalties are set by each state's rules and orders, so read yours on the Authority's site.
- The update is easy when bookings, approvals and site photos are recorded as they happen, not rebuilt on the last day.
What is a RERA quarterly update?
When a project is registered, the promoter gets a login for the state Authority's website and creates a web page for the project. Section 11(1) of the Real Estate (Regulation and Development) Act, 2016 says the promoter enters the project details there for public viewing. Several of those details have to be kept up to date every quarter.
That page is what a buyer, a bank and the Authority read. The quarterly update is how it stays true while the building goes up.
What does section 11(1) ask for each quarter?
Four items are written with the word quarterly. First, the list of the number and types of apartments or plots booked. Second, the list of the number of garages booked. Third, the list of approvals taken and the approvals still pending after the commencement certificate. Fourth, the status of the project. A fifth clause covers other information the Authority specifies by regulation.
The Act sets what is reported. The rules of each state then set how: the form, the supporting photographs, and how long after the quarter ends the filing is due.
Who files it, and where?
The promoter files it, on the project's page of the state Authority's portal, with the login and password received at registration. Many promoters hand the data entry to an in-house compliance person or a consultant. The duty stays with the promoter.
Each state has its own portal and its own rules. Use the Authority that registered your project, and read the orders posted on its site. If you hold projects in more than one state, keep a separate calendar for each.
When is it due, and what if it is late?
The deadline is a state rule, and states change both the window and the penalty. West Bengal shows how specific the rules can get. Its December 2024 order cites the state's rules on what a quarterly update contains, requires earlier quarters to be filled in as well, and states the penalty for late filing under the Act.
Open the current order on your Authority's website, put the dates into your calendar, and confirm them with your lawyer or compliance adviser.
What should be ready before the quarter closes?
Three records decide how painful the update is. A booking list that matches the sales register: unit number, type, and date. An approvals list with each approval taken, each one pending, and who is chasing it. A construction log with dated photographs for each building and for the common areas.
West Bengal's rules, as the Authority's December 2024 order quotes them, ask in the status section for the construction status of each building and each floor with photographs, and for approvals received, applied for and still to apply for. Other states ask for different detail, but the same three records feed all of them.
How does a builder make this routine?
Treat the quarter as a report from systems you already run. The unit inventory in a builder's CRM knows how many units are booked and of which type. A shared approvals tracker holds the approvals, with an owner for each pending one. A site engineer uploads dated photographs to the project record weekly.
On the last working days of the quarter, a report pulls those three records into the layout your Authority's form asks for. Your team checks it, then enters it on the portal. Softivum builds this reporting view as part of custom CRM development, and uses workflow automation to remind the site team to upload photos and the approvals owner to update the list.
How does the update connect to your marketing?
A buyer who scans the QR code on your advertisement reaches the project page. If the quarterly status there is old, the advertisement and the page disagree. The construction updates your WhatsApp bot sends should match what was filed, and what a real estate chatbot should handle shows how the bot links to the Authority's page instead of repeating its own numbers.
What a property advertisement must show under RERA covers the advertising duty that sends buyers to that page, and the RERA QR code covers the Maharashtra rule for reaching it with one scan.
What feeds each quarterly item
| Section 11(1) item | Where the data lives | Who owns it |
|---|---|---|
| Apartments or plots booked, by type | Unit inventory and booking register | Sales head |
| Garages booked | Covered garage allotments (open parking excluded, section 2(y)) | Sales operations |
| Approvals taken and pending | Approvals tracker | Liaison or compliance lead |
| Status of the project | Construction log with dated photographs | Project manager |
How to run a quarterly update
Read your Authority's current order and rules
Note the form, the photographs asked for and the deadline after quarter end.
Freeze the booking and approvals lists
On the quarter's last day, export the booking register and the approvals tracker.
Collect the dated photographs
Pull the latest site photographs for each building and common area from the construction log.
Fill the portal form from the export
Enter the figures and upload the photographs on the project's page, using the promoter login.
Check the public page and file the proof
Open the project's public page, confirm the new quarter shows, and save a copy with the date.
Before you submit a quarterly update
- You have read the current order and the deadline on your Authority's website
- Bookings by type and garages booked match the sales register
- Approvals taken and pending are listed, each pending one with an owner
- Dated photographs cover each building and the common areas
- Earlier quarters are filled in where your Authority requires them
- The public page shows the new quarter and a dated copy is saved
Sources